Adding a new bathroom to your home is a big job that needs careful planning. At Trinity Design and Construction, we’re experts in helping you through the process. Our team can handle everything from figuring out what you need in your new bathroom to getting it all done just right. We’ll work closely with you to understand what you want and make sure your new bathroom turns out exactly how you imagined. With Trinity Design and Construction, you can trust that your new bathroom will be comfortable, practical, and exactly what you wanted.

Trinity Design and Construction Logo

bathroom construction

SCOPE

As we embark on your bathroom renovation project, we want to ensure clarity and alignment on the scope of work. Here are the key aspects to consider as we move forward:

Project Objectives

Objectives 400x300

Purpose: Identify the main goals of the renovation (e.g., updating aesthetics, increasing functionality, improving accessibility).

Expectations: Define what you expect to achieve with the renovation, such as modernizing fixtures, increasing storage, or creating a spa-like atmosphere

Space Assessment

Current Layout: Assess the existing bathroom layout and determine what works and what needs to change.

Laser Measurement

Size and Dimensions: Measure the bathroom to understand the space constraints and possibilities for reconfiguration.

Design & Style

Bathroom Design & Style 400x400

Design Theme: Choose a design style (modern, traditional, minimalist, etc.) that you want for your renovated bathroom.

Color Scheme: Decide on a color palette that complements the overall design and creates the desired ambiance.

Structural Changes

Wall Removal/Additions: Determine if any walls need to be removed or added to change the layout.

Bathroom Structural 400 x 300

Floor Plan Modifications: Decide if the floor plan will be altered significantly (e.g., moving the toilet, shower, or sink).

Window and Door Changes: Consider adding, removing, or resizing windows and doors for better light, ventilation, or accessibility.

Budget & Timeline

Time and Money 400x300

Budget: Set a clear budget for the entire project, including a contingency for unexpected expenses.

Timeline: Create a realistic timeline for each phase of the renovation, from demolition to final touches.

Cost 400x300

Plumbing & Electrical

Plumbing Changes: Assess whether existing plumbing needs to be upgraded or re-routed to accommodate new fixtures.

Trinity Design and Construct Indoor Spaces Bathroom Structural Material 300x300

Electrical Upgrades: Determine the need for new electrical wiring, outlets, lighting fixtures, or any other electrical components.

Fixtures & Fittings

Toilet: Decide if the toilet will be replaced or relocated.

Bathtub/Shower: Choose between keeping, upgrading, or replacing the bathtub and/or shower. Consider adding new features like a rain showerhead or a freestanding tub.

Trinity Design and Construct Indoor Spaces Bathroom Taps 2 400x300

Vanity and Sink: Select new vanity units and sinks that fit the new design and layout.

Materials & Finishes

Flooring: Decide on the type of flooring materials (tiles, stone, vinyl, etc.).

Trinity Design and Construct Indoor Spaces Bathroom Flooring 400x300

Wall Coverings: Choose wall finishes such as tiles, paint, or waterproof panels.

Countertops: Select durable and aesthetically pleasing materials for countertops.

Storage Solutions

Cabinetry: Plan for new or upgraded cabinets and drawers to enhance storage.

Shelving: Consider built-in shelves, niches, or other storage solutions.

Trinity Design and Construct Indoor Spaces Bathroom Vanity 400x300

Lighting & Ventilation

Trinity Design and Construct Indoor Spaces Bathroom Mirror Options 400x300

Lighting Plan: Design a lighting plan that includes task lighting, ambient lighting, and accent lighting.

Ventilation: Ensure proper ventilation through exhaust fans or windows to prevent moisture buildup.

Regulations & Permits

Permits: Identify any necessary permits required for structural, plumbing, or electrical work.

Building Codes: Ensure the renovation complies with local building codes and regulations.

regulations 400x300

Accessibility & Safety

Universal Design: Incorporate features for accessibility such as grab bars, non-slip flooring, and walk-in showers.

Bathroom safety 400x300

Safety Features: Plan for adequate safety measures to prevent accidents and injuries.

Sustainability

eco friendly bathroom 400x300

Eco-Friendly Options: Consider sustainable materials and energy-efficient fixtures.

Water Conservation: Install water-saving fixtures like low-flow toilets and showerheads.

Personalization

Custom Features: Add any custom features or personal touches that reflect your style and preferences.

Technology Integration: Consider integrating smart bathroom technology for enhanced convenience and functionality.

Trinity Design and Construct Indoor Spaces Bathroom Heating Options 400x300
Trinity Design and Construct Indoor Spaces Bathroom Bathtub 300x300

Plumbing Fixtures

Toilet, Sink (vanity or pedestal), Bathtub or shower, Faucets (sink, bathtub, shower), Showerhead, Drainage pipes and fittings

Trinity Design and Construct Indoor Spaces Bathroom Electrical 2 300x300

Electrical Fixtures

Lighting fixtures (ceiling lights, vanity lights, recessed lights), Outlets and switches, Exhaust fan, Heated towel rail (optional), Underfloor heating (optional)

Trinity Design and Construct Indoor Spaces Bathroom Vanity 300x300

Cabinetry and Storage

Bathroom vanity or cabinet, Medicine cabinet or mirror with storage, Shelving units or storage racks

Trinity Design and Construct Indoor Spaces Bathroom Door Lock 300x300

Hardware and Fittings

Door handles and locks, Cabinet hardware (knobs, handles), Shower door or curtain rod, Bathroom accessories (soap dishes, toothbrush holders)

Trinity Design and Construct Indoor Spaces Bathroom Exhaust Fan 300x300

Ventilation and Plumbing Accessories

Ventilation ducts and fittings, P-trap and other plumbing fittings, Water supply lines and connectors

Trinity Design and Construct Indoor Spaces Bathroom Shower Bench 300x300

Fixtures for Accessibility (optional, if needed)

Grab bars, Handheld showerhead, Raised toilet seat, Shower bench or seat

Trinity Design and Construct Indoor Spaces Bathroom Structural Material 300x300

Structural Materials

Lumber (for framing), Gyprock/plasterboard, Studs, joists, and beams, Insulation (for walls and ceilings)

Trinity Design and Construct Indoor Spaces Bathroom Grouting 300x300

Miscellaneous Materials

Grout and caulk (for tiles and joints), Adhesive (for installing tiles and flooring), Screws, nails, and fasteners, Paint primer and sealer, Trim and molding

Trinity Design and Construct Indoor Spaces Bathroom Accessories Decor 300x300

Accessories and Decor

Towel bars or hooks, Toilet paper holder, Shower caddy or organizer, Bathroom rug or mat, Window treatments (curtains, blinds)

Trinity Design and Construct Indoor Spaces Bathroom Flooring 300x300

Flooring Materials

Tiles (ceramic, porcelain, natural stone), Vinyl flooring, Laminate flooring, Hardwood flooring (not recommended for bathrooms due to moisture)

Trinity Design and Construct Indoor Spaces Bathroom Wallpaper 300x300

Wall Finishes

Tiles (for walls, backsplashes, and shower enclosures), Paint Wallpaper (moisture-resistant)

Trinity Design and Construct Indoor Spaces Bathroom Waterproofing 300x300

Waterproofing Materials

Waterproofing membrane, Waterproofing tape, Sealing compounds (for joints and seams)

Trinity Design and Construct Indoor Spaces Bathroom Bathtub 300x300

Plumbing Fixtures

Toilet, Sink (vanity or pedestal), Bathtub or shower, Faucets (sink, bathtub, shower), Showerhead, Drainage pipes and fittings

Trinity Design and Construct Indoor Spaces Bathroom Electrical 2 300x300

Electrical Fixtures

Lighting fixtures (ceiling lights, vanity lights, recessed lights), Outlets and switches, Exhaust fan, Heated towel rail (optional), Underfloor heating (optional)

Trinity Design and Construct Indoor Spaces Bathroom Vanity 300x300

Cabinetry and Storage

Bathroom vanity or cabinet, Medicine cabinet or mirror with storage, Shelving units or storage racks

Trinity Design and Construct Indoor Spaces Bathroom Door Lock 300x300

Hardware and Fittings

Door handles and locks, Cabinet hardware (knobs, handles), Shower door or curtain rod, Bathroom accessories (soap dishes, toothbrush holders)

Trinity Design and Construct Indoor Spaces Bathroom Exhaust Fan 300x300

Ventilation and Plumbing Accessories

Ventilation ducts and fittings, P-trap and other plumbing fittings, Water supply lines and connectors

Trinity Design and Construct Indoor Spaces Bathroom Shower Bench 300x300

Fixtures for Accessibility (optional, if needed)

Grab bars, Handheld showerhead, Raised toilet seat, Shower bench or seat

Trinity Design and Construct Indoor Spaces Bathroom Structural Material 300x300

Structural Materials

Lumber (for framing), Gyprock/plasterboard, Studs, joists, and beams, Insulation (for walls and ceilings)

Trinity Design and Construct Indoor Spaces Bathroom Grouting 300x300

Miscellaneous Materials

Grout and caulk (for tiles and joints), Adhesive (for installing tiles and flooring), Screws, nails, and fasteners, Paint primer and sealer, Trim and molding

Trinity Design and Construct Indoor Spaces Bathroom Accessories Decor 300x300

Accessories and Decor

Towel bars or hooks, Toilet paper holder, Shower caddy or organizer, Bathroom rug or mat, Window treatments (curtains, blinds)

Trinity Design and Construct Indoor Spaces Bathroom Flooring 300x300

Flooring Materials

Tiles (ceramic, porcelain, natural stone), Vinyl flooring, Laminate flooring, Hardwood flooring (not recommended for bathrooms due to moisture)

Trinity Design and Construct Indoor Spaces Bathroom Wallpaper 300x300

Wall Finishes

Tiles (for walls, backsplashes, and shower enclosures), Paint Wallpaper (moisture-resistant)

Trinity Design and Construct Indoor Spaces Bathroom Waterproofing 300x300

Waterproofing Materials

Waterproofing membrane, Waterproofing tape, Sealing compounds (for joints and seams)

Defining the scope of a bathroom renovation involves detailed planning and consideration of various elements to ensure the project meets your objectives, stays within budget, and is completed on time. Clear scope definition helps in managing expectations, coordinating efforts, and achieving a successful renovation.

bathroom construction

TRADES & SERVICES

General Contractor

Oversees the entire project, coordinates with subcontractors, and manages timelines and budgets.

Plumber

Installs and maintains plumbing systems including pipes, fixtures, water heaters, and drainage.

Electrician

Installs wiring, electrical panels, outlets, switches, lighting fixtures, and ensures electrical safety.

Carpenter

Constructs frameworks, partitions, floors, doors, windows, and other wooden structures.

Tiler

Installs ceramic, porcelain, or natural stone tiles for floors, walls, and other surfaces.

Painter

Applies paint, stain, and other finishes to surfaces inside and outside the home.

Waterproofer

Applies waterproofing membranes to ensure moisture protection in wet areas such as showers, floors, and walls. Ensures compliance with waterproofing standards.

Plasterboard / Gyprock Installer

Installs and finishes plasterboard/gyprock board for walls and ceilings.

Glass Installer

Installs glass shower screens, mirrors, and other glass fixtures. Ensures proper fitting and sealing for safety and durability.

Flooring Installer

Installs flooring materials such as tiles, vinyl, laminate, hardwood, or engineered wood flooring. Ensures proper subfloor preparation and installation techniques.

Cabinetmaker/Joiner

Constructs custom cabinetry, vanities, and storage solutions to fit the specific dimensions and design requirements of the bathroom.

HVAC Technician

Installs and maintains heating, ventilation, and air conditioning systems for climate control.

Demolition Contractor

Removes existing structures, fixtures, or materials to prepare the site for renovation or new construction.

Architect / Designer

Designs the layout and structure of the home, ensuring compliance with building codes and regulations.

Interior Designer

Provides expertise in interior decoration, layout, and aesthetics to enhance the overall design of the home.

Project Manager

Coordinates scheduling, manages subcontractors, communicates with the client, and ensures the project stays on track and within budget.

General Contractor

Oversees the entire project, coordinates with subcontractors, and manages timelines and budgets.

Plumber

Installs and maintains plumbing systems including pipes, fixtures, water heaters, and drainage.

Electrician

Installs wiring, electrical panels, outlets, switches, lighting fixtures, and ensures electrical safety.

Carpenter

Constructs frameworks, partitions, floors, doors, windows, and other wooden structures.

Tiler

Installs ceramic, porcelain, or natural stone tiles for floors, walls, and other surfaces.

Painter

Applies paint, stain, and other finishes to surfaces inside and outside the home.

Waterproofer

Applies waterproofing membranes to ensure moisture protection in wet areas such as showers, floors, and walls. Ensures compliance with waterproofing standards.

Plasterboard / Gyprock Installer

Installs and finishes plasterboard/gyprock board for walls and ceilings.

Glass Installer

Installs glass shower screens, mirrors, and other glass fixtures. Ensures proper fitting and sealing for safety and durability.

Flooring Installer

Installs flooring materials such as tiles, vinyl, laminate, hardwood, or engineered wood flooring. Ensures proper subfloor preparation and installation techniques.

Cabinetmaker / Joiner

Constructs custom cabinetry, vanities, and storage solutions to fit the specific dimensions and design requirements of the bathroom.

HVAC Technician

Installs and maintains heating, ventilation, and air conditioning systems for climate control.

Demolition Contractor

Removes existing structures, fixtures, or materials to prepare the site for renovation or new construction.

Architect / Designer

Designs the layout and structure of the home, ensuring compliance with building codes and regulations.

Interior Designer

Provides expertise in interior decoration, layout, and aesthetics to enhance the overall design of the home.

Project Manager

Coordinates scheduling, manages subcontractors, communicates with the client, and ensures the project stays on track and within budget.

Engaging qualified and experienced professionals in each of these trades and services is essential for a successful bathroom construction or renovation project. Hiring licensed and insured contractors ensures quality workmanship and compliance with relevant building codes and regulations.

bathroom construction

PERMITS & REGULATIONS

When adding a new bathroom or renovating an existing one in Sydney, Australia, several permits and regulations need to be considered to ensure compliance with local building codes and standards. Here are some key factors to keep in mind:

  1. Building Permit: You typically need a building permit for any significant alterations or additions to your property, including adding or renovating a bathroom. This permit ensures that your project meets the requirements of the Building Code of Australia (BCA) and other relevant regulations.

  2. Plumbing Permit: A plumbing permit is required for any plumbing work associated with the new bathroom or renovation. This includes installing new fixtures, pipes, drains, and connections to the existing plumbing system. Plumbing work must be carried out by a licensed plumber.

  3. Waterproofing Requirements: Bathrooms must be properly waterproofed to prevent water damage and mold growth. The Australian Standard AS 3740 outlines the requirements for waterproofing wet areas, including bathrooms. Waterproofing must be done by a licensed waterproofing contractor, and a compliance certificate should be obtained upon completion.

  4. Ventilation: Proper ventilation is essential to prevent moisture buildup and mold growth in bathrooms. The Building Code of Australia (BCA) specifies ventilation requirements for bathrooms, including minimum ventilation rates and the installation of exhaust fans.

  5. Electrical Work: If your bathroom renovation involves electrical work, such as installing new lighting, outlets, or heated towel rails, you’ll need to comply with electrical safety regulations. All electrical work must be performed by a licensed electrician, and any new installations must meet Australian wiring standards.

  6. Accessibility: If you’re renovating or adding a bathroom to accommodate individuals with disabilities or special needs, you may need to comply with accessibility standards outlined in the Disability (Access to Premises – Buildings) Standards 2010.

  7. Heritage Considerations: If your property is located within a heritage conservation area or is a heritage-listed building, you may need additional approvals or permits for any alterations or additions, including bathroom renovations. You’ll need to consult with your local council’s heritage officer to ensure compliance with heritage regulations.

  8. Waste Management: Proper disposal of construction waste and any hazardous materials generated during the renovation process is important. You may need to arrange for skip bins or other waste disposal services and ensure that waste is disposed of in accordance with local regulations.

  9. Neighbourhood Impact: Consider any potential impact your renovation may have on neighbours, such as noise, dust, or disruptions to parking. Communicate with your neighbours about your renovation plans and try to minimize any inconvenience.

  10. Engage Professionals: It’s essential to engage qualified professionals, such as architects, builders, plumbers, electricians, and waterproofing contractors, who are familiar with local regulations and can ensure that your project complies with all necessary permits and standards.

 

Before starting your bathroom renovation or addition, it’s advisable to consult with your local council or a building certifier to confirm the specific permits and regulations that apply to your project in Sydney. They can provide guidance and assistance throughout the permit application process.

Trinity Design and Construction Logo

bathroom construction

SPEED

Navigating the rhythm of delivery is paramount when estimating the timeline for building your bathroom. We meticulously work out schedules, considering the optimal timeframe for both you and our team. Drawing from best practices and leveraging insights from similar completed projects, we tailor a timeline that aligns with regulatory requirements, council rules, and your financial considerations.

Time Estimation Process

Precision is key in estimating the ideal duration. We consider:

  • Project Scope: Detailed planning and assessment of all tasks involved.
  • Regulatory Requirements: Ensuring compliance with council rules and obtaining necessary permits.
  • Quality Standards: Maintaining high standards without rushing the process.

Commitment to Timely Delivery

We understand the urgency and are committed to delivering promptly without compromising on quality. Your deadline becomes our benchmark, and we strive to meet it efficiently.

Realistic Timelines

Patience is a virtue, and quality often takes time. We ensure realistic timelines, providing transparency about the process, potential obstacles, and any unforeseen delays. Clear communication helps manage expectations and ensures smooth progress.

Collaboration and Understanding

Your understanding and collaboration are vital. We value your input on:

  • Preferred Timeline: Your desired completion date.
  • Flexibility: How long you are prepared to wait for quality results.

Defining Your Deadline

Let’s work together to define a realistic deadline. By aligning our schedules and maintaining open communication, we can ensure the successful realization of your vision within the bounds of excellence and efficiency.

bathroom construction

TIME ESTIMATES

Small Bathroom Renovation (Approximately 4-6 square meters)

  • Estimated Renovation Duration: 2-4 weeks
  • Description: A small bathroom renovation typically involves cosmetic updates and minor structural modifications. Tasks may include removing old fixtures, updating plumbing and electrical systems, installing new fixtures and finishes, and completing final touches. With efficient scheduling and coordination, a small bathroom renovation can be completed in approximately 2 to 4 weeks.

Medium Bathroom Renovation (Approximately 7-9 square meters):

  • Estimated Renovation Duration: 3-5 weeks
  • Description: A medium-sized bathroom renovation requires more extensive updates compared to a small bathroom. This may involve replacing fixtures, updating plumbing and electrical systems, installing new flooring and wall finishes, and making moderate structural changes. The larger size and scope of work typically extend the renovation duration, ranging from 3 to 5 weeks.

Large Bathroom Renovation (Approximately 10+ square meters):

  • Estimated Renovation Duration: 4-6 weeks
  • Description: A large bathroom renovation represents a significant project with comprehensive updates and potential structural modifications. Tasks may include replacing all fixtures, updating plumbing and electrical systems, installing new flooring and wall finishes, and making significant layout changes. The complexity and size of the project generally require a longer renovation duration, typically ranging from 4 to 6 weeks or more.

These estimated building durations provide a general guideline for planning the construction timeline for adding a new bathroom of different sizes in Sydney, Australia. Actual building durations may vary based on factors such as the specific scope of the project, site conditions, and unforeseen challenges encountered during construction. Working with experienced contractors or renovation specialists can help ensure that the project stays on schedule and is completed efficiently and effectively.

Small Bathroom Addition (Approximately 4-6 square meters)

  • Estimated Building Duration: 4-6 weeks
  • Description: A small bathroom addition typically involves minimal structural modifications and can be completed within a relatively short timeframe. The construction process includes tasks such as framing, plumbing and electrical work, installation of fixtures and finishes, and final inspections. With efficient scheduling and coordination, a small bathroom addition can be completed in approximately 4 to 6 weeks.

Medium Bathroom Addition (Approximately 7-9 square meters):

  • Estimated Building Duration: 6-8 weeks
  • Description: A medium-sized bathroom addition requires more extensive construction work compared to a small bathroom, including additional framing, plumbing, and electrical installations. The larger size may also involve more intricate design elements and finishes. As a result, the building duration for a medium bathroom addition is typically longer, ranging from 6 to 8 weeks.

Large Bathroom Addition (Approximately 10+ square meters):

  • Estimated Building Duration: 8-12 weeks
  • Description: A large bathroom addition represents a significant project with substantial construction requirements. The larger size necessitates extensive framing, plumbing, electrical, and finishing work, as well as potential structural modifications. The complexity of the project and the need for meticulous attention to detail may extend the building duration, typically ranging from 8 to 12 weeks or more.

These estimated building durations provide a general guideline for planning the construction timeline for adding a new bathroom of different sizes in Sydney, Australia. Actual building durations may vary based on factors such as the specific scope of the project, site conditions, and unforeseen challenges encountered during construction. Working with experienced contractors or renovation specialists can help ensure that the project stays on schedule and is completed efficiently and effectively.

bathroom construction

BUILDING TASKS

Building Project Timeline for Medium Size Bathroom Addition

Planning Icon White
Week 1

Initial Consultation and Planning:

• Task: Discuss renovation goals, budget, and design preferences. • Duration: 1-2 weeks • Dependencies: None • Service Provider: General Contractor or Bathroom Designer

Certification Icon White
Week 1-2

Obtain Necessary Permits:

• Task: Apply for building permits and approvals from local authorities. • Duration: 1-2 weeks • Dependencies: Initial consultation and planning • Service Provider: General Contractor or Permit Expeditor

Demolition Icon White
Week 2-3

Demolition and Site Preparation

• Task: Remove old fixtures, fittings, and finishes from the bathroom. • Duration: 1 week • Dependencies: Obtain necessary permits • Service Provider: Demolition Contractor

Plumbing Icon White
Week 3-4

Assessment of Plumbing and Electrical Systems

• Task: Evaluate existing plumbing and electrical systems for any necessary upgrades or repairs. • Duration: 1 week • Dependencies: Demolition and removal of existing fixtures • Service Provider: Plumber, Electrician

Structural Build Icon White
Week 4-5

Structural Modifications (if needed):

• Task: Make any structural modifications required to accommodate new fixtures or layout changes. • Duration: 1-2 weeks • Dependencies: Assessment of plumbing and electrical systems • Service Provider: Carpenter

WaterProofing Icon White
Week 5

Waterproofing and Moisture Barrier Installation:

• Task: Apply waterproofing membranes to walls, floors, and shower areas. • Duration: 1 week • Dependencies: Structural modifications (if needed) • Service Provider: Waterproofing Specialist

Tiling Icon White
Week 6

Tiling Installation

o Task: Install floor and wall tiles using appropriate adhesives and grouting materials. o Duration: 2-3 weeks o Dependencies: Waterproofing o Service Provider: Tiler

Bath Icon White
Week 6-7

Installation of New Fixtures and Fittings:

• Task: Install new plumbing fixtures, such as sinks, toilets, showers, and bathtubs, as well as accessories like towel rails and toilet paper holders. • Duration: 1-2 weeks • Dependencies: Waterproofing and moisture barrier installation • Service Provider: Plumber

Power Icon White
Week 7

Electrical Fixture Installation:

• Task: Install new lighting fixtures, outlets, switches, and exhaust fans. • Duration: 1-2 weeks • Dependencies: Waterproofing and moisture barrier installation • Service Provider: Electrician

Painting Icon White
Week 7-8

Floor and Wall Finishing:

• Task: Install new flooring materials (e.g., tiles, vinyl, laminate) and wall finishes (e.g., paint, wallpaper). • Duration: 1-2 weeks • Dependencies: Installation of new fixtures and fittings, electrical fixture installation • Service Provider: Flooring Installer, Painter

Washbasin Icon White
Week 8

Cabinetry and Vanity Installation

• Task: Install new cabinetry, vanities, and storage solutions. • Duration: 1-2 weeks • Dependencies: Floor and wall finishing • Service Provider: Cabinetmaker/Joiner

Open Plan Living Icon White
Week 9

Final Touches and Cleanup

• Task: Perform any remaining touch-ups, clean the area thoroughly, and remove debris from the site. • Duration: 1 week • Dependencies: Cabinetry and vanity installation • Service Provider: General Contractor or Cleaning Crew

Inspection Icon White
Week 9

Final Inspection and Approval:

• Task: Schedule a final inspection with local building authorities to ensure compliance with building codes and regulations. • Duration: 1 week • Dependencies: Completion of all tasks • Service Provider: Building Inspector or Permit Expeditor

Planning Icon White
Week 1

Initial Consultation and Planning:

• Task: Discuss renovation goals, budget, and design preferences. • Duration: 1-2 weeks • Dependencies: None • Service Provider: General Contractor or Bathroom Designer

Certification Icon White
Week 1-2

Obtain Necessary Permits:

• Task: Apply for building permits and approvals from local authorities. • Duration: 1-2 weeks • Dependencies: Initial consultation and planning • Service Provider: General Contractor or Permit Expeditor

Demolition Icon White
Week 2-3

Demolition and Site Preparation

• Task: Remove old fixtures, fittings, and finishes from the bathroom. • Duration: 1 week • Dependencies: Obtain necessary permits • Service Provider: Demolition Contractor

Plumbing Icon White
Week 3-4

Assessment of Plumbing and Electrical Systems

• Task: Evaluate existing plumbing and electrical systems for any necessary upgrades or repairs. • Duration: 1 week • Dependencies: Demolition and removal of existing fixtures • Service Provider: Plumber, Electrician

Structural Build Icon White
Week 4-5

Structural Modifications (if needed):

• Task: Make any structural modifications required to accommodate new fixtures or layout changes. • Duration: 1-2 weeks • Dependencies: Assessment of plumbing and electrical systems • Service Provider: Carpenter

WaterProofing Icon White
Week 5

Waterproofing and Moisture Barrier Installation:

• Task: Apply waterproofing membranes to walls, floors, and shower areas. • Duration: 1 week • Dependencies: Structural modifications (if needed) • Service Provider: Waterproofing Specialist

Tiling Icon White
Week 6

Tiling Installation

o Task: Install floor and wall tiles using appropriate adhesives and grouting materials. o Duration: 2-3 weeks o Dependencies: Waterproofing o Service Provider: Tiler

Bath Icon White
Week 6-7

Installation of New Fixtures and Fittings:

• Task: Install new plumbing fixtures, such as sinks, toilets, showers, and bathtubs, as well as accessories like towel rails and toilet paper holders. • Duration: 1-2 weeks • Dependencies: Waterproofing and moisture barrier installation • Service Provider: Plumber

Power Icon White
Week 7

Electrical Fixture Installation:

• Task: Install new lighting fixtures, outlets, switches, and exhaust fans. • Duration: 1-2 weeks • Dependencies: Waterproofing and moisture barrier installation • Service Provider: Electrician

Painting Icon White
Week 7-8

Floor and Wall Finishing:

• Task: Install new flooring materials (e.g., tiles, vinyl, laminate) and wall finishes (e.g., paint, wallpaper). • Duration: 1-2 weeks • Dependencies: Installation of new fixtures and fittings, electrical fixture installation • Service Provider: Flooring Installer, Painter

Washbasin Icon White
Week 8

Cabinetry and Vanity Installation

• Task: Install new cabinetry, vanities, and storage solutions. • Duration: 1-2 weeks • Dependencies: Floor and wall finishing • Service Provider: Cabinetmaker/Joiner

Open Plan Living Icon White
Week 9

Final Touches and Cleanup

• Task: Perform any remaining touch-ups, clean the area thoroughly, and remove debris from the site. • Duration: 1 week • Dependencies: Cabinetry and vanity installation • Service Provider: General Contractor or Cleaning Crew

Inspection Icon White
Week 9

Final Inspection and Approval:

• Task: Schedule a final inspection with local building authorities to ensure compliance with building codes and regulations. • Duration: 1 week • Dependencies: Completion of all tasks • Service Provider: Building Inspector or Permit Expeditor

Building Project Timeline for Medium Size Bathroom Addition

Planning Icon White
Week 1

Initial Consultation and Planning:

o Task: Discuss project scope, budget, and design preferences. o Duration: 1-2 weeks o Dependencies: None o Service Provider: General Contractor or Bathroom Designer

Certification Icon White
Week 1-2

Obtain Necessary Permits:

o Task: Apply for building permits and approvals from local authorities. o Duration: 1-2 weeks o Dependencies: Initial consultation and planning o Service Provider: General Contractor or Permit Expeditor

Demolition Icon White
Week 2-3

Demolition and Site Preparation

o Task: Remove existing fixtures, fittings, and finishes from the designated bathroom area. o Duration: 1 week o Dependencies: Obtain necessary permits o Service Provider: Demolition Contractor

Plumbing Icon White
Week 3-4

Rough Plumbing Installation:

o Task: Install plumbing lines and connections for fixtures such as sinks, toilets, showers, and bathtubs. o Duration: 1-2 weeks o Dependencies: Demolition and site preparation o Service Provider: Plumber

Power Icon White
Week 4-5

Rough Electrical Installation

o Task: Install electrical wiring, outlets, switches, and lighting fixtures according to the approved plan. o Duration: 1-2 weeks o Dependencies: Demolition and site preparation o Service Provider: Electrician

Structural Build Icon White
Week 5-6

Framing and Structural Modifications

o Task: Construct framing for walls, floors, and ceilings, and make any necessary structural modifications. o Duration: 1-2 weeks o Dependencies: Rough plumbing and electrical installation o Service Provider: Carpenter

WaterProofing Icon White
Week 6

Waterproofing

o Task: Apply waterproofing membranes to walls, floors, and shower areas to prevent moisture damage. o Duration: 1 week o Dependencies: Framing and structural modifications o Service Provider: Waterproofing Specialist

Tiling Icon White
Week 6

Tiling Installation

o Task: Install floor and wall tiles using appropriate adhesives and grouting materials. o Duration: 2-3 weeks o Dependencies: Waterproofing o Service Provider: Tiler

Washbasin Icon White
Week 7-8

Cabinetry and Vanity Installation:

o Task: Install custom cabinetry, vanities, and storage solutions according to the approved design. o Duration: 1-2 weeks o Dependencies: Framing and structural modifications o Service Provider: Cabinetmaker/Joiner

Bath Icon White
Week 8

Fixture Installation:

o Task: Install plumbing fixtures such as sinks, toilets, showers, and bathtubs, as well as accessories like towel rails and toilet paper holders. o Duration: 1-2 weeks o Dependencies: Rough plumbing installation o Service Provider: Plumber

Power Icon White
Week 9

Final Electrical and Lighting Installation

o Task: Connect electrical fixtures and lighting, and perform final testing to ensure functionality and safety. o Duration: 1-2 weeks o Dependencies: Rough electrical installation o Service Provider: Electrician

Painting Icon White
Week 9

Painting and Finishing

o Task: Install flooring materials such as tiles, vinyl, laminate, hardwood, or engineered wood flooring. o Duration: 1-2 weeks (Planning and Delivery) o Dependencies: Cabinetry and vanity installation, final electrical and lighting installation o Service Provider: Flooring Installer

Open Plan Living Icon White
Week 10

Final Touches and Cleanup

o Task: Perform any remaining touch-ups, clean the area thoroughly, and remove debris from the site. o Duration: 1 week o Dependencies: Painting and finishing, flooring installation o Service Provider: General Contractor or Cleaning Crew

Inspection Icon White
Week 10

Final Inspection and Approval:

o Task: Schedule a final inspection with local building authorities to ensure compliance with building codes and regulations. o Duration: 1 week o Dependencies: Completion of all tasks o Service Provider: Building Inspector or Permit Expeditor

Planning Icon White
Week 1

Initial Consultation and Planning:

o Task: Discuss project scope, budget, and design preferences. o Duration: 1-2 weeks o Dependencies: None o Service Provider: General Contractor or Bathroom Designer

Certification Icon White
Week 1-2

Obtain Necessary Permits:

o Task: Apply for building permits and approvals from local authorities. o Duration: 1-2 weeks o Dependencies: Initial consultation and planning o Service Provider: General Contractor or Permit Expeditor

Demolition Icon White
Week 2-3

Demolition and Site Preparation

o Task: Remove existing fixtures, fittings, and finishes from the designated bathroom area. o Duration: 1 week o Dependencies: Obtain necessary permits o Service Provider: Demolition Contractor

Plumbing Icon White
Week 3-4

Rough Plumbing Installation:

o Task: Install plumbing lines and connections for fixtures such as sinks, toilets, showers, and bathtubs. o Duration: 1-2 weeks o Dependencies: Demolition and site preparation o Service Provider: Plumber

Power Icon White
Week 4-5

Rough Electrical Installation

o Task: Install electrical wiring, outlets, switches, and lighting fixtures according to the approved plan. o Duration: 1-2 weeks o Dependencies: Demolition and site preparation o Service Provider: Electrician

Structural Build Icon White
Week 5-6

Framing and Structural Modifications

o Task: Construct framing for walls, floors, and ceilings, and make any necessary structural modifications. o Duration: 1-2 weeks o Dependencies: Rough plumbing and electrical installation o Service Provider: Carpenter

WaterProofing Icon White
Week 6

Waterproofing

o Task: Apply waterproofing membranes to walls, floors, and shower areas to prevent moisture damage. o Duration: 1 week o Dependencies: Framing and structural modifications o Service Provider: Waterproofing Specialist

Tiling Icon White
Week 6

Tiling Installation

o Task: Install floor and wall tiles using appropriate adhesives and grouting materials. o Duration: 2-3 weeks o Dependencies: Waterproofing o Service Provider: Tiler

Washbasin Icon White
Week 7-8

Cabinetry and Vanity Installation:

o Task: Install custom cabinetry, vanities, and storage solutions according to the approved design. o Duration: 1-2 weeks o Dependencies: Framing and structural modifications o Service Provider: Cabinetmaker/Joiner

Bath Icon White
Week 8

Fixture Installation:

o Task: Install plumbing fixtures such as sinks, toilets, showers, and bathtubs, as well as accessories like towel rails and toilet paper holders. o Duration: 1-2 weeks o Dependencies: Rough plumbing installation o Service Provider: Plumber

Power Icon White
Week 9

Final Electrical and Lighting Installation

o Task: Connect electrical fixtures and lighting, and perform final testing to ensure functionality and safety. o Duration: 1-2 weeks o Dependencies: Rough electrical installation o Service Provider: Electrician

Painting Icon White
Week 9

Painting and Finishing

o Task: Install flooring materials such as tiles, vinyl, laminate, hardwood, or engineered wood flooring. o Duration: 1-2 weeks (Planning and Delivery) o Dependencies: Cabinetry and vanity installation, final electrical and lighting installation o Service Provider: Flooring Installer

Open Plan Living Icon White
Week 10

Final Touches and Cleanup

o Task: Perform any remaining touch-ups, clean the area thoroughly, and remove debris from the site. o Duration: 1 week o Dependencies: Painting and finishing, flooring installation o Service Provider: General Contractor or Cleaning Crew

Inspection Icon White
Week 10

Final Inspection and Approval:

o Task: Schedule a final inspection with local building authorities to ensure compliance with building codes and regulations. o Duration: 1 week o Dependencies: Completion of all tasks o Service Provider: Building Inspector or Permit Expeditor

Trinity Design and Construction Logo

bathroom construction

QUALITY

Understanding the delicate interplay between scope, budget, and schedule is pivotal in crafting the perfect bathroom. Each aspect influences the other, and achieving harmony is our expertise.

Defining the Scope

As we define the scope of your bathroom renovation, we balance your aspirations with practical considerations. Your vision sets the stage, and we ensure it aligns with budget constraints and desired features. This dynamic equilibrium directly influences the quality of the end result.

Luxury Bathroom

In the realm of luxury, the sky’s the limit. We align the scope with premium features and materials, acknowledging the impact on both budget and schedule. It’s about delivering an unparalleled experience, where every detail contributes to the opulence you envision.

Best Bathroom

For the best option, balance is key. We harmonize scope, budget, and schedule to provide a solution that epitomizes quality within a pragmatic budget and a carefully planned timeline. Here, the interplay ensures durability, aesthetics, and cost-effectiveness coalesce seamlessly.

Better Bathroom

Within the better option, we manage the triangle of scope, budget, and schedule to deliver a result that encapsulates quality without compromising practicality. It’s about finding that sweet spot where your vision thrives within reasonable parameters.

Good Bathroom

Even in the realm of good, where affordability is a priority, we navigate the tension gracefully. We ensure quality doesn’t take a backseat, offering a robust solution that adheres to standards without escalating costs unnecessarily.

Commitment to Excellence

Understanding this balance is where our commitment to excellence truly shines. The delicate choreography between scope, budget, and schedule is our craft, ensuring that the quality we deliver is not just a promise but a tangible reality in every facet of your project.

By working together and considering these factors, we can create a bathroom that not only meets but exceeds your expectations. We’re here to guide you through every step, ensuring your vision becomes a reality.

Trinity Design and Construct Indoor Spaces Bathroom Bathtub 300x300

Plumbing Fixtures

Toilet, Sink (vanity or pedestal), Bathtub or shower, Faucets (sink, bathtub, shower), Showerhead, Drainage pipes and fittings

Trinity Design and Construct Indoor Spaces Bathroom Electrical 2 300x300

Electrical Fixtures

Lighting fixtures (ceiling lights, vanity lights, recessed lights), Outlets and switches, Exhaust fan, Heated towel rail (optional), Underfloor heating (optional)

Trinity Design and Construct Indoor Spaces Bathroom Vanity 300x300

Cabinetry and Storage

Bathroom vanity or cabinet, Medicine cabinet or mirror with storage, Shelving units or storage racks

Trinity Design and Construct Indoor Spaces Bathroom Door Lock 300x300

Hardware and Fittings

Door handles and locks, Cabinet hardware (knobs, handles), Shower door or curtain rod, Bathroom accessories (soap dishes, toothbrush holders)

Trinity Design and Construct Indoor Spaces Bathroom Exhaust Fan 300x300

Ventilation and Plumbing Accessories

Ventilation ducts and fittings, P-trap and other plumbing fittings, Water supply lines and connectors

Trinity Design and Construct Indoor Spaces Bathroom Shower Bench 300x300

Fixtures for Accessibility (optional, if needed)

Grab bars, Handheld showerhead, Raised toilet seat, Shower bench or seat

Trinity Design and Construct Indoor Spaces Bathroom Structural Material 300x300

Structural Materials

Lumber (for framing), Gyprock/plasterboard, Studs, joists, and beams, Insulation (for walls and ceilings)

Trinity Design and Construct Indoor Spaces Bathroom Grouting 300x300

Miscellaneous Materials

Grout and caulk (for tiles and joints), Adhesive (for installing tiles and flooring), Screws, nails, and fasteners, Paint primer and sealer, Trim and molding

Trinity Design and Construct Indoor Spaces Bathroom Accessories Decor 300x300

Accessories and Decor

Towel bars or hooks, Toilet paper holder, Shower caddy or organizer, Bathroom rug or mat, Window treatments (curtains, blinds)

Trinity Design and Construct Indoor Spaces Bathroom Flooring 300x300

Flooring Materials

Tiles (ceramic, porcelain, natural stone), Vinyl flooring, Laminate flooring, Hardwood flooring (not recommended for bathrooms due to moisture)

Trinity Design and Construct Indoor Spaces Bathroom Wallpaper 300x300

Wall Finishes

Tiles (for walls, backsplashes, and shower enclosures), Paint Wallpaper (moisture-resistant)

Trinity Design and Construct Indoor Spaces Bathroom Waterproofing 300x300

Waterproofing Materials

Waterproofing membrane, Waterproofing tape, Sealing compounds (for joints and seams)

Trinity Design and Construct Indoor Spaces Bathroom Bathtub 300x300

Plumbing Fixtures

Toilet, Sink (vanity or pedestal), Bathtub or shower, Faucets (sink, bathtub, shower), Showerhead, Drainage pipes and fittings

Trinity Design and Construct Indoor Spaces Bathroom Electrical 2 300x300

Electrical Fixtures

Lighting fixtures (ceiling lights, vanity lights, recessed lights), Outlets and switches, Exhaust fan, Heated towel rail (optional), Underfloor heating (optional)

Trinity Design and Construct Indoor Spaces Bathroom Vanity 300x300

Cabinetry and Storage

Bathroom vanity or cabinet, Medicine cabinet or mirror with storage, Shelving units or storage racks

Trinity Design and Construct Indoor Spaces Bathroom Flooring 300x300

Flooring Materials

Tiles (ceramic, porcelain, natural stone), Vinyl flooring, Laminate flooring, Hardwood flooring (not recommended for bathrooms due to moisture)

Trinity Design and Construct Indoor Spaces Bathroom Wallpaper 300x300

Wall Finishes

Tiles (for walls, backsplashes, and shower enclosures), Paint Wallpaper (moisture-resistant)

Trinity Design and Construct Indoor Spaces Bathroom Waterproofing 300x300

Waterproofing Materials

Waterproofing membrane, Waterproofing tape, Sealing compounds (for joints and seams)

Trinity Design and Construct Indoor Spaces Bathroom Structural Material 300x300

Structural Materials

Lumber (for framing), Drywall or plasterboard, Studs, joists, and beams, Insulation (for walls and ceilings)

Trinity Design and Construct Indoor Spaces Bathroom Grouting 300x300

Miscellaneous Materials

Grout and caulk (for tiles and joints), Adhesive (for installing tiles and flooring), Screws, nails, and fasteners, Paint primer and sealer, Trim and molding

Trinity Design and Construct Indoor Spaces Bathroom Accessories Decor 300x300

Accessories and Decor

Towel bars or hooks, Toilet paper holder, Shower caddy or organizer, Bathroom rug or mat, Window treatments (curtains, blinds)

Trinity Design and Construct Indoor Spaces Bathroom Door Lock 300x300

Hardware and Fittings

Door handles and locks, Cabinet hardware (knobs, handles), Shower door or curtain rod, Bathroom accessories (soap dishes, toothbrush holders)

Trinity Design and Construct Indoor Spaces Bathroom Exhaust Fan 300x300

Ventilation and Plumbing Accessories

Ventilation ducts and fittings, P-trap and other plumbing fittings, Water supply lines and connectors

Trinity Design and Construct Indoor Spaces Bathroom Shower Bench 300x300

Fixtures for Accessibility (optional, if needed)

Grab bars, Handheld showerhead, Raised toilet seat, Shower bench or seat

Here’s a comprehensive list of various features and options for a bathroom, including different choices and variations:

This comprehensive list covers a wide range of features and options available for designing and customizing your bathroom to suit your preferences and needs. Depending on your budget, space, and personal style, you can mix and match different elements to create a functional and stylish bathroom that reflects your individual taste and lifestyle

Here are some key quality requirements to consider:

1. Materials Quality

  • Durable Flooring: Choose high-quality, water-resistant flooring materials such as porcelain or ceramic tiles, natural stone, or high-quality vinyl.
  • Moisture-Resistant Wall Materials: Use moisture-resistant drywall (greenboard) or cement board behind tiles to prevent mold and mildew.
  • Premium Fixtures: Invest in high-quality fixtures for the sink, shower, and toilet. Look for reputable brands known for durability and reliability.
  • Countertops: Select durable and non-porous materials like quartz, granite, or solid surface for countertops to withstand daily wear and tear.

2. Workmanship

  • Professional Installation: Hire experienced professionals for plumbing, electrical work, and tile installation to ensure proper fitting and long-lasting results.
  • Precision Tiling: Ensure tiles are laid out evenly with consistent grout lines to avoid uneven surfaces and water seepage.
  • Smooth Finishes: Ensure smooth and seamless finishes on all surfaces, including walls, floors, and countertops.

3. Waterproofing

  • Shower and Tub Areas: Properly waterproof shower and tub areas using waterproof membranes or underlayment to prevent water damage.
  • Sealants: Use high-quality sealants around fixtures, countertops, and joints to prevent water infiltration.

4. Ventilation

  • Effective Ventilation System: Install a high-quality exhaust fan to remove moisture and prevent mold growth. Consider fans with humidity sensors for automatic operation.
  • Ducting: Ensure proper ducting of the ventilation system to the outside to effectively expel moist air.

5. Plumbing

  • Reliable Plumbing Fixtures: Choose faucets, showerheads, and valves made from corrosion-resistant materials like brass or stainless steel.
  • Leak Prevention: Ensure all plumbing connections are secure and leak-free. Consider pressure balancing valves to prevent scalding.
  • Water Efficiency: Opt for high-efficiency toilets and low-flow faucets and showerheads to conserve water without compromising performance.

6. Electrical

  • Safe Electrical Work: Ensure all electrical installations comply with local codes. Use GFCI (Ground Fault Circuit Interrupter) outlets in wet areas for safety.
  • Adequate Lighting: Install high-quality, moisture-resistant lighting fixtures. Ensure proper placement for task lighting around the vanity and general lighting for the entire space.

7. Durability

  • High-Quality Hardware: Use durable hardware for cabinets and drawers, such as soft-close hinges and drawer slides.
  • Long-Lasting Paint: Choose paint that is mold and mildew resistant for walls and ceilings.

8. Functionality and Accessibility

  • Ergonomic Design: Ensure the layout is functional and ergonomic, with easy access to all fixtures.
  • Accessibility Features: Incorporate features like grab bars, non-slip flooring, and walk-in showers to enhance safety and accessibility.

9. Aesthetics and Style

  • Consistent Design: Maintain a consistent design theme and color scheme throughout the bathroom for a cohesive look.
  • Quality Finishes: Use high-quality finishes for all visible surfaces, including fixtures, hardware, and accessories.

10. Sustainability

  • Eco-Friendly Materials: Choose sustainable and environmentally friendly materials where possible.
  • Energy Efficiency: Install energy-efficient lighting and ventilation systems to reduce energy consumption.

bathroom construction

FEATURES & OPTIONS

Trinity Design and Construct Indoor Spaces Bathroom Lighting Options 300x300

Lighting Options

Ceiling-mounted light fixtures (recessed lights, flush mounts), Pendant lights or chandeliers, Wall sconces or vanity lights, LED mirror lights, Under-cabinet lighting, Dimmer switches for adjustable lighting

Trinity Design and Construct Indoor Spaces Bathroom Mirror Options 300x300

Mirror Options

Framed mirror, Frameless mirror, Medicine cabinet with mirrored door, Magnifying mirror (wall-mounted or countertop)

Trinity Design and Construct Indoor Spaces Bathroom Wallpaper Options 300x300

Design Elements

Accent tiles or mosaic patterns, Decorative wall panels or wainscoting, Statement wallpaper or wall decals, Glass partition or half-wall divider, Planters or greenery for a spa-like ambiance

Trinity Design and Construct Indoor Spaces Bathroom Flooring Options 300x300

Flooring Options

Ceramic tiles, Porcelain tiles, Natural stone tiles (marble, granite, travertine), Vinyl flooring (sheet or tile), Laminate flooring, Engineered wood flooring, Cork flooring, Heated flooring (electric or hydronic)

Trinity Design and Construct Indoor Spaces Bathroom Heating Options 300x300

Heating Options

Heated towel rack or towel warmer, Radiant floor heating, Wall-mounted electric heater, Baseboard heater, Infrared heat lamp

Trinity Design and Construct Indoor Spaces Bathroom Storage Options 300x300

Storage and Organization Options

Built-in shelving or niches, Medicine cabinet or mirror with storage, Over-the-toilet cabinet or shelving unit, Vanity with drawers or cabinets, Wall-mounted storage cabinet, Linen closet or tower

Trinity Design and Construct Indoor Spaces Bathroom BathTub Options 300x300

Bath Options

Built-in bathtub, Freestanding bathtub, Soaking tub, Clawfoot tub, Corner bathtub, Jacuzzi or whirlpool tub, Walk-in bathtub (with door)

Trinity Design and Construct Indoor Spaces Bathroom Shower Options 300x300

Shower Options

Single-head shower, Dual-head shower (with handheld and overhead showerheads), Rainfall showerhead Body jets or massage shower panels, Steam shower, Walk-in shower (curbless or with a low threshold), Shower enclosure or glass door, Frameless glass shower enclosure

Trinity Design and Construct Indoor Spaces Bathroom Vanity Options 300x300

Vanity Options

Single vanity, Double vanity, Floating vanity, Wall-mounted vanity, Freestanding vanity, Custom-built vanity, Vessel sink vanity, Undermount sink vanity

Trinity Design and Construction Logo

bathroom

COSTS

Arriving at the final estimated cost for your bathroom renovation is the culmination of a meticulous process that intertwines scope, schedule, and desired quality. It’s not just a number; it’s the result of careful consideration to ensure every aspect aligns with your vision and practical parameters.

Understanding the Cost Analysis

As we delve into the intricacies of your project’s scope, schedule, and the quality you aspire to achieve, we consider various factors that contribute to the overall cost. Key elements include:

  • Scope of Work: Detailed planning of what needs to be done, from demolition to final touches.
  • Project Schedule: Timeline for completing each phase of the renovation.
  • Quality Standards: Desired materials, fixtures, and finishes.

Contributing Factors

Several critical factors shape the financial landscape of your project:

  • Environmental Considerations: Assessments to ensure sustainable practices and compliance with environmental regulations.
  • Regulatory Requirements: Obtaining necessary permits and adhering to construction rules, including fire resistance and noise proofing.
  • Foundation and Footing Requirements: Ensuring the structural integrity of your bathroom renovation.

Navigating Approvals and Permits

Dependence on council approvals, permits, and construction regulations adds another layer of complexity. We navigate through these variables to provide a comprehensive cost estimate, ensuring compliance and avoiding delays.

The Art of Negotiation

This is the juncture where negotiation becomes essential. We fine-tune the scope, schedule, and quality to tailor the project to your needs. Your financial comfort is our priority, and we are committed to transparent communication throughout this process.

Final Cost Estimate

The final estimated cost is not just a number on paper; it’s a reflection of our dedication to delivering a project that aligns with your vision, meets regulatory standards, and respects your budget constraints. This stage is where collaboration takes center stage. Let’s work together to adjust and ensure that the final cost mirrors the perfect synthesis of your aspirations and practical realities.

Your bathroom renovation is not just a construction endeavor; it’s a tailored experience. The estimated cost is the ticket to bringing your vision to life.

bathroom

COST INFLUENCERS

Size and Scope of the Project

The size and complexity of the new bathroom will have a significant impact on the overall cost. Larger bathrooms with more fixtures and custom features will generally cost more to build than smaller, more straightforward designs.

Labor Costs

Labor Costs: Labor costs can vary depending on factors such as local labor rates, the availability of skilled workers, and the complexity of the construction work required. Plumbing, electrical, and carpentry work will all contribute to the labor costs of the project.

Bathroom Location

  • Upstairs: Adding a bathroom upstairs typically involves more complex construction tasks, such as reinforcing floor joists, rerouting plumbing and electrical lines, and addressing potential structural concerns. Access to the upper level may also require additional labor and equipment, particularly if there are narrow staircases or limited space for maneuvering materials. These factors can contribute to higher labor and material costs compared to adding a bathroom on the ground floor.
  • Downstairs: Installing a bathroom on the ground floor may be more straightforward in terms of construction and accessibility. Existing plumbing and electrical infrastructure may be more readily accessible, reducing the need for extensive modifications. Additionally, if the new bathroom is located near exterior walls, ventilation and drainage requirements may be easier to meet, potentially lowering costs compared to upstairs installations.

Acessibility Requirements

    • Accessible Design: If your home requires accessibility features, such as wider doorways, barrier-free showers, or wheelchair-friendly layouts, incorporating these elements into the new bathroom design will incur additional costs. These features may necessitate specialized fixtures, structural modifications, and careful planning to ensure compliance with accessibility standards.
    • Standard Design: Homes with standard layouts and dimensions typically involve fewer design complexities and may have existing infrastructure that can be easily adapted for the new bathroom. This can help streamline the construction process and keep costs more manageable compared to homes requiring extensive modifications for accessibility.

Type of Dwelling

  • Single-Family Home: Adding a bathroom to a single-family home provides more flexibility in terms of design and construction, as there are typically fewer restrictions compared to multi-unit dwellings. Homeowners have more control over the layout, fixtures, and finishes, which can impact costs based on their preferences and budget.
  • Townhouse/Complex/Unit: In multi-unit dwellings such as townhouses, condominium complexes, or apartment units, adding a new bathroom may involve additional considerations, such as obtaining approval from homeowners' associations, complying with shared utility systems, or coordinating with neighboring units. These factors can introduce logistical challenges and administrative requirements that may affect project costs.

Site Access & Conditions

  • Side Access: If the new bathroom requires materials or equipment to be brought in through side access points rather than directly through the home, additional labor and logistics may be necessary. Access limitations can impact the efficiency of the construction process and potentially increase costs associated with transportation and manual handling of materials.
  • Site Conditions: Site-specific factors, such as soil stability, drainage issues, or proximity to utilities, can influence the complexity and cost of construction. Addressing site-related challenges, such as excavating for new plumbing lines or addressing water intrusion issues, may require specialized expertise and resources, adding to the overall project expenses.

Materials and Fixtures

The cost of materials and fixtures for the new bathroom can vary widely depending on factors such as quality, brand, and style. High-end finishes and fixtures will generally cost more than budget-friendly options.

Plumbing and Electrical Work

If the new bathroom requires extensive plumbing and electrical work, such as installing new water supply lines, drainage pipes, or wiring for lighting and outlets, these costs will add to the overall project expenses.

Permits and Regulations

Obtaining permits and complying with building codes and regulations can incur additional costs. Permit fees, inspection fees, and any necessary modifications to ensure compliance with local regulations will all contribute to the total project cost.

Structural Modifications

If the new bathroom requires structural modifications to the existing home, such as reinforcing floors, walls, or ceilings, these additional construction tasks will increase the overall cost of the project.

Ventilation and HVAC

Proper ventilation is essential in bathrooms to prevent moisture buildup and mold growth. Installing exhaust fans or ventilation systems, as well as integrating with the home's HVAC system, may incur additional costs.

Accessibility Features

If the new bathroom needs to be accessible to individuals with disabilities or mobility challenges, incorporating features such as grab bars, walk-in showers, or wider doorways may increase the project cost.

Design Complexity

Intricate design elements, such as custom tile work, specialty lighting, or unique fixtures, will add to the overall cost of the project. Simplifying the design or opting for standard finishes can help control costs.

Contingency Fund

It's essential to budget for unexpected expenses or changes that may arise during the construction process. Setting aside a contingency fund of around 10-20% of the total project cost can help cover unforeseen expenses and prevent budget overruns.

bathroom

COST ESTIMATES

Low Cost Price Icon Blue

Budget Estimate

From:

$8,000

$1,333 per m2

Up To:

$15,000

$2,500 per m2

* Based on Standard Bathroom Size of 4-6 m2. See below for detailed break-down

Medium Cost Price Icon Blue

Standard Estimate

From:

$15,000

$2,500 per m2

Up To:

$35,000

$5,833 per m2

* Based on Standard Bathroom Size of 4-6 m2. See below for detailed break-down

High Cost Price Icon Blue

Premium Estimate

From:

$35,000

$5,833 per m2

Up To:

$47,940+

$7,990+ per m2

* Based on Standard Bathroom Size of 4-6 m2. See below for detailed break-down

Budget Renovation (Lowest Extimation)

  • Cost Range: $8,000 - $15,000
  • Average Cost per Square Meter: $1333 - $2,500 AUD per square meter

  • Average Bathroom Size: Typically around 4 to 6 square meters

  • Description: A budget renovation focuses on essential updates and cost-saving measures while working within the existing layout and structure of the bathroom. This might include:
    • Basic cosmetic updates (e.g., painting, regrouting)
    • Repairing or replacing worn fixtures (e.g., faucets, showerheads)
    • Refinishing or resurfacing surfaces (e.g., bathtub, vanity)
    • Installing budget-friendly flooring and lighting
    • Minimal plumbing or electrical work
    • Standard quality materials and finishes

Standard Renovation (Mid-Range)

  • Cost Range: $15,000 - $35,000 AUD

    • Average Cost per Square Meter: $2,500 - $5,833 AUD per square meter

    • Average Bathroom Size: Typically around 4 to 6 square meters

    Description: A standard renovation offers a balance between affordability and quality, providing more comprehensive updates and improvements to enhance the overall look and functionality of the bathroom. This might include:

    • Upgrading fixtures and fittings (e.g., replacing bathtub or shower, toilet, vanity)
    • Installing new flooring and wall tiles
    • Updating lighting fixtures for better illumination
    • Some plumbing and electrical work (e.g., relocating fixtures, adding outlets)
    • Semi-custom cabinetry or quality vanity unit
    • Moderate structural changes or layout adjustments
    • Quality materials and finishes

Premium Renovation (High-End)

  • Cost Range: $35,000+ 

    • Average Cost per Square Meter: $5,833+  per square meter

    • Average Bathroom Size: Typically around 4 to 6 square meters

    Description: A premium renovation offers top-of-the-line features, luxury finishes, and high-quality craftsmanship for a truly upscale bathroom experience. This might include:

    • High-end fixtures and fittings (e.g., designer bathtub or shower, wall-hung toilet, custom vanity with premium stone countertop)
    • Luxury materials such as natural stone or designer tiles
    • Custom-built cabinetry or bespoke vanity design
    • Designer or architectural lighting fixtures
    • Extensive plumbing and electrical work (e.g., upgrading plumbing lines, installing smart fixtures)
    • Luxury amenities and features (e.g., steam shower, soaking tub, underfloor heating)
    • Customized design elements and personalized touches
    • Exceptional attention to detail and superior craftsmanship

bathroom

COST CAVEATS

These estimates provide a breakdown of the average costs for renovating an existing bathroom in Sydney, Australia, across different budget tiers. The baseline costs are derived from the average costs incured for an average bathroom with a floor size equating to  4 – 6 square meters. These base cost estimates are Actual costs and will vary based on factors such as the size of the bathroom, specific design choices, the quality of the bathroom fixtures and furniture, and the extent of renovation required. 

bathroom

COST MODELLING

The Trinity Team brings years of experience to the design and solution phase of your project. Let’s talk so we can organize a detailed review of your requirements and your current bathroom. We can create a comprehensive breakdown of the items and tasks needed, helping you obtain accurate quotes tailored to your specific needs.

bathroom

Low Cost Price Icon Blue

Budget Estimate

From:

$11,000

$1,833 per m2

Up To:

$20,550

$3,425 per m2

* Based on Standard Bathroom Size of 4-6 m2. See below for detailed break-down

Medium Cost Price Icon Blue

Standard Estimate

From:

$20,550

$3,425 per m2

Up To:

$41,100

$6,850 per m2

* Based on Standard Bathroom Size of 4-6 m2. See below for detailed break-down

High Cost Price Icon Blue

Premium Estimate

From:

$41,100

$6,850 per m2

Up To:

$56,310+

$9,385+ per m2

* Based on Standard Bathroom Size of 4-6 m2. See below for detailed break-down

Budget Addition (Lowest Extimation)

Cost Range: $11,000 - $20,550

Average Cost per Square Meter: $1,833 - $3,425 per square meter

Average Bathroom Size: Typically around 4 to 6 square meters

Description: A budget renovation for a typical 4 to 6 square meter bathroom in Sydney would cost approximately $8,000 to $15,000 AUD. This tier offers basic upgrades and cost-saving measures without extensive customization or premium finishes.

Standard Addition (Mid-Range)

  • Cost Range: $20,550 - $41,100 AUD

    Average Cost per Square Meter: $3,425 - $6,850 per square meter

    Average Bathroom Size: Typically around 4 to 6 square meters

    Description: A standard renovation for a typical 4 to 6 square meter bathroom in Sydney would cost approximately $15,000 to $30,000 AUD. This tier offers upgraded fixtures, quality finishes, and moderate customization to enhance the overall look and functionality of the bathroom.

Premium Addition (High-End)

  • Cost Range: $41,100+

    Average Cost per Square Meter: $6,850+ per square meter

    Average Bathroom Size: Typically around 4 to 6 square meters

    Description: A premium renovation for a typical 4 to 6 square meter bathroom in Sydney would cost $30,000 AUD or more. This investment provides top-of-the-line features, luxury finishes, and high-quality craftsmanship, resulting in a truly upscale bathroom experience.

bathroom

COST CAVEATS

These estimates provide a breakdown of the average costs for adding an addition bathroom to your home in Sydney, Australia, across different budget tiers. The baseline costs are derived from the average costs incured for an average bathroom with a floor size equating to  4 – 6 square meters. These base cost estimates will vary based on factors such as the size of the bathroom, specific design choices, the quality of the bathroom fixtures and furniture, and the extent of renovation required.

bathroom

COST MODELLING

The Trinity Team brings years of experience to the design and solution phase of your project. Let’s talk so we can organize a detailed review of your requirements and your current bathroom. We can create a comprehensive breakdown of the items and tasks needed, helping you obtain accurate quotes tailored to your specific needs.

VALUE ESTIMATES

Budget Renovation (Lowest Extimation)

  • Extra Value Added: An estimated increase of $5,000 - $10,000 AUD to the home's market value.
  • Description: While the increase in home value may be more modest compared to higher-tier renovations, a budget renovation can still add significant value by enhancing the functionality and aesthetics of the bathroom. This can translate to a higher resale price and increased market appeal for the home.

Standard Renovation (Mid-Range)

  • Extra Value Added: An estimated increase of $15,000 - $25,000 AUD to the home's market value.
  • Description: A standard renovation offers a balanced approach, providing comprehensive updates and improvements to the bathroom that enhance its overall appeal and desirability. This can result in a more substantial increase in market value compared to budget renovations.

Premium Renovation (High-End)

  • Extra Value Added: An estimated increase of $30,000 - $50,000+ AUD to the home's market value.
  • Description: A premium renovation delivers top-of-the-line features, luxury finishes, and exceptional craftsmanship, significantly enhancing the home's market value. This can attract high-end buyers seeking luxury amenities and customized design elements, potentially leading to a faster sale at a higher price point.

In summary, while all renovations can add value to a standard home, the extent of value added varies depending on the quality and features of the renovation. Budget renovations enhance functionality and appearance at a lower cost, standard renovations offer a balance of affordability and quality, and premium renovations provide luxury features and exceptional craftsmanship that can significantly increase the home’s market value.

Budget Addition (Lowest Extimation)

  • Value Added: An estimated increase of $10,000 - $20,000 AUD to the home's resale value.
  • Description: With a budget addition, the modest increase in home value reflects the basic upgrades and essential functionality of the new bathroom. While the added value may be more modest compared to higher-tier additions, it still enhances the overall appeal and marketability of the home, potentially leading to a higher resale price.

Standard Addition (Mid-Range)

  • Value Added: An estimated increase of $20,000 - $40,000 AUD to the home's resale value.
  • Description: For a standard addition, the moderate increase in home value reflects the balanced approach, offering upgraded fixtures, quality finishes, and enhanced functionality. This tier adds significant market appeal and desirability to the home, potentially resulting in a higher resale price compared to homes without newly added bathrooms.

Premium Addition (High-End)

  • Value Added: An estimated increase of $40,000 - $80,000+ AUD to the home's resale value.
  • Description: A premium addition commands a substantial increase in home value, reflecting the top-of-the-line features, luxury finishes, and exceptional craftsmanship of the new bathroom. This tier adds significant market value and distinguishes the home as a high-end property, potentially leading to a premium resale price and attracting buyers seeking luxury amenities and customized design elements.

These estimated cost value estimations provide a guideline for understanding the potential costs of adding a new bathroom to a home in Sydney, Australia, across different budget tiers. Actual costs may vary based on factors such as the size and complexity of the project, specific design choices, and market conditions. Consulting with experienced contractors or renovation specialists can help you obtain accurate quotes tailored to your specific project needs.

Trinity Design and Construction Logo

bathroom

PORTFOLIO

space

SOLUTIONS

OUR

SPECIALITY

New Green Icon

New Builds

New construction built from the ground up. Making your plans a reality

Repair Green Icon

Maintenance & Repairs

Fixing broken or damaged components and restoring them to their previous state

Replace Green Icon

Replacements

Installing new components to enhance or replace worn-out elements, restoring them to their previous functional state

Improve Green Icon

Improvements

Enhancing existing components to optimize performance and functionality

Renovate Green Icon

Renovations

Revitalizing spaces through comprehensive component updates and enhancements

Design Icon Green

Design

Crafting innovative and functional building design solutions tailored to clients' needs

Trinity Design and Construction Logo

making

TIME

Considering a bathroom renovation? Let’s talk! We’ve helped many clients achieve their dream bathrooms, and we’re confident we can help you too. From practical upgrades to custom designs, we’re here to offer guidance and have a friendly conversation about how we can meet your specific needs. No pressure – just give us a call, and let’s create a bathroom that perfectly fits your lifestyle.

Joshua@trinitydc.com.au

0430 393 681

Contact Us

    If you already have a clear idea of what you need or even have design plans you’d like us to review, let’s talk. We’ll provide you with a quote on the estimated complexity, cost, and duration of your bathroom renovation. Give us a call or send us your information, and we’ll get back to you within one working day.

    Contact Us

      We’re dedicated to making your vision a reality. Our planning process is all about collaboration. Together, we’ll create a practical plan tailored to your needs and preferences. We’ll discuss your requirements and design preferences to ensure every detail aligns with your style.

      Budget-Friendly Quality

      Your budget matters, but it won’t cramp your style. We find cost-effective solutions to maximize your budget without compromising quality, ensuring your dream space becomes a reality.

      Realistic Timeframes

      Timeframes are important, and we respect that. Our planning ensures a realistic schedule with no unnecessary delays – just a well-thought-out timeline.

      Transparency and Trust

      Transparency is key. Our clear process keeps you informed every step of the way. Trust and confidence are crucial, and we’re committed to building both with you.

      Stress-Free Planning

      We break down the planning process into manageable steps, ensuring a stress-free journey. Celebrate each milestone as we turn your vision into reality.

      Ready to Start?

      Let’s begin the conversation, explore ideas, and craft a plan that is uniquely yours. Give us a call to start making your dream space a reality.

      Contact Us

        At Trinity D&C, our bathroom renovation process ensures a seamless journey from planning to reality:

        Efficient Planning

        We fine-tune your project plan based on your preferences, ensuring smooth and efficient execution.

        Skilled Construction

        Our expert team guarantees quality craftsmanship, providing regular updates on progress to keep you informed.

        Timely Execution

        We prioritize deadlines, committing to on-time project delivery without compromising on quality.

        Quality Assurance

        Rigorous checks maintain our high standards, ensuring your complete satisfaction with the finished product.

        Final Inspection

        A thorough inspection precedes the on-time delivery of your completed bathroom, ensuring everything meets our standards and your expectations.

        Post-Delivery Support

        Our commitment extends beyond delivery. We offer ongoing support to ensure your continued satisfaction.

        Ready to start your bathroom renovation journey with Trinity D&C? Let’s make your vision a reality.

        Contact Us

          Trinity Design and Construction Logo

          Why People Recommend Trinity Design & Construction

          google
          Melike Temel
          16 09 2023

          The best company I have ever dealt with. I can’t recommend these boys enough. 100/10 Always on time and their work is amazing. Thank you for everything you have done.

          google
          Paul Jay
          28 08 2023

          We had a custom designed wooden deck built and moulded to the shape of the pool. The results was amazing, Trinity Design and Construction were very professional and very plesant to work with.

          google
          Kimbo Davo
          30 06 2023

          Trinity Design & Construction built our backyard retaining wall and also our large decking area. They are highly professional, on time, polite, informative and their workmanship was outstanding. Highly recommend.

          google
          Peacock Family
          13 05 2023

          We found the team at Trinity Design & Construct to be really easy to work with. Their attention to detail was second to none and we wouldn't hesitate to recommend them.

          google

          Trinity Design & Construct came out to repair a leaking window that required a strip down of one side of the house, they were on time, courteous, and left the site clean and tidy, most importantly; the repair worked! Thanks to Josh and the team for all your hard work, we will definitely be using their services again.

          google

          We employed Trinity D&C to undertake many differing construction items in the build of our new home. Each task was undertaken with the quality, expertise, & efficiency that we were looking for. As I was also the Building Designer of the project, I was particularly impressed with the level of interest they took in the aesthetic detail that was required, & then the formulating of the construction methodology. Many a tradesperson would have simply looked for the simplest & most expedient way of completing the job. I have nothing but praise for Trinity D&C, & am forever grateful for their efforts. Thank you. Dan Briffa (Home Owner & Designer)